18 Sep

New Control Room Evolution

New Control Room Evolution

Recently, Synergy completed a complete control room remodel for a client.  Along with the updated look and increased storage space, the new control room provides:

  • Modern boiler control Human Machine Interface
  • Improved workflow
  • Improved reaction time
  • Improved screens and display, allowing for faster dissemination of information
  • Low-voltage lighting, reducing fatigue and eye strain of operators

Click here to see a slideshow of all the work that went into this incredible transformation.

Control Room Evolution
June 6: Demolition begins and control console is moved to a temp location.

Evolution of Control Room
June 22: The remodel, rough in.

Control room on July 9th and nearly finished.
July 17th: Major components are in place.

Completion: July 17th.
Completion: July 17th.